The Petro-Processors, Inc. site remediation
continued normally during the last six months. Sixty-three recovery wells on the
Brooklawn site produced an average of 536 gallons per day of water and 31 gallons per day of free-phase organics. There were no deviations to the operating specification.
The Brooklawn RPA Addendum F was submitted to USEPA and LADEQ for approval on June
22, 2006. LADEQ has recommended approval to USEPA.
The on-site workers completed 6 years and 346,869 man-hours with no OSHA recordable
injuries on June 28.
William C. Dawson, President
Disclaimer: Unsolicited applications for employment or resumes are not maintained by NPC Services, Inc. NPC accepts applications on company-supplied forms only, and will not accept applications except for a specific position, and then only when an opening is advertised. All applications that do not meet this requirement will be returned.